1. F A C I L I T Y P R O J E C T S

F A C I L I T Y P R O J E C T S

 

F A C I L I T Y P R O J E C T S

P R O G R A M S T A T U S R E P O R T

JULY 2 0 0 3

Weston Ranch High School Office

MANTECA UNIFIED SCHOOL DISTRICT

 

mUSD

Manteca Unified School District

Facilities Program

Program Status Report

Overview…………………..as of July 24, 2003

The current 2003 Construction program includes the follow i ng types of facility w o rk:

• New Schools

o W e ston Ranch High School Phase I pg 3

o W e ston Ranch High School Phase II pg 7

o W a lter W oodward School Phase I Adm i n/Library/MP room pg 10

o W a

lter W oodward School Phase II Classrooms pg 14

o W a lter W oodward School Phase III landscaping pg 15

o Veritas School pg 16

• Construction-Additions to Existing Sites

o August

Knodt Multipurpose Room pg 18

o Sequoia Multipurpose Room pg 20

o Sierra High School Stadium pg 22

o W e ston Ranch Joint Use Gym pg 24

o

W e ston Ranch Swim m i ng Pool pg 25

o W e ston Ranch High School Stadium pg 26

o 4 Relocatables at Nile Garden

pg 28

o 6 Relocatables at

Great Valley pg 30

o 9 Relocatables at New Haven pg 32

o Relocatables at Sierra, Lincoln, Sequoia pg 33

o Relocatables at Lathrop, August Knodt, Stella Brockm an, French Cam p pg 36

• On the Planning Maps

o Lathrop High School pg 38

o 20 Relocatables various locations pg 40

o Calla W a ter line pg 41

o District Office Bus W a sh sh

pg 42

o East Union Band room Conversion pg 43

o East Union Modernization pg 44

1

o French Cam p Modernization pg 45

 

mUSD

Manteca Unified School District

o Great Valley Annex pg 46

o Lathrop Com m unity Multipurpose room pg 49

o Manteca High School Field House pg 50

o Lathrop Area School #1 pg 51

o Nile Garden Gas Line and Parking lot pg 54

o Nile Garden Modernization pg 55

o Lathrop Area School #2 pg 56

o Robertson Property pg 58

o R u s t i c E l e m e n t a r y p g 5 9

o Sequoia Old Multipurpose room Conversion pg 61

o Shasta Modernization pg 62

o Sierra Staffroom Conversion pg 63

o Stella Brockm an Annex pg 64

o Tesoro Annex pg 66

o North Manteca School pg 68

o W e ston Ranch Phase III pg 70

o W i dm er Property School pg 73

• Just Completed

o George Kom u re School pg 75

o East Union Classroom Addition pg 74

o Parking lot im provem e nts at New Haven pg 78

o Sierra Classroom Addition pg 79

o Sierra High School Stadium Lights pg 83

2

 

mUSD

Manteca Unified School District

Program Status by Individual School Site………………

WESTON RANCH HIGH SCHOOL –PHASE I

 

The school is located on a fifty (50) acre site. Phase I includes an adm i nistration building,

library, ten (10) classroom s, six (6) science labs, seven (7) business labs, six (6) classroom s,

three (3) shops, cafeteria, large gym nasium , boys’ locker room , and a girls’ locker room . Phase I

of the high school should house approxim a tely 1,000 students.

• General Contractor: F & H Construction

• Contract Date: October 24, 2001

• Original Contract Sum : $19,711,000.00

• Start Date: Novem b er 12, 2001

• Net Contract Change by Change Orders: $480,942.31

• Current Contract Sum Including All Approved Change Orders: $20,191,942.31

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $20,191,942.31

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: 2.4%

• Total Am ount Paid to Contractor to Date: $19,135,104.94

• Total Am ount Held in Escrow Account as Retention to Date: $1,056,837.37

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: $0

• Percentage of Project Com p lete: 100%

• Anticipated Com p letion Date: May 2003

• Building Square Footage 107,428

• Covered W a lkway Square Footage 3 7 , 4 6 7

• Total Square Footage 144,895

• Construction Cost Per Square Foot $139.36

• Funding Sources: Fund 25 (Developer Fees)

Fund 35 (State Funds)

CFD 1 (Mello Roos)

CFD 2 (Mello Roos)

CFD 3 (Mello Roos)

Reim bursem e nts from Architect/Engineer/Developer

3

 

mUSD

Manteca Unified School District

• Estim ated Project Budget SITE $1,890,000.00

PLANS $1,350,000.00

CONSTRUCTION $23,514,175.91

INSPECTIONS $300,000.00

TESTS $165,000.00

FURN & EQUIPMENT $600,000.00

CONTINGENCIES $1,834,320.73

TOTAL $29,653,496.64

View of the Quad Area looking West. Administration Building on left, Library in Center and

10 Classrooms on right.

4

 

mUSD

Manteca Unified School District

Weston Ranch High School

Phase I, exterior view of front lobby of

Main Gymnasium. Exterior painting is

complete.

Phase I, sanding of floors in the Main

Gymnasium to prep for finish

application and painting of game

lines. Interior basketball equipment a

score boards have been installed.

5

 

mUSD

Manteca Unified School District

View of the interior of science classrooms

in the North Wing. Case w o rk and

flooring complete.

Interior view of the new Library

building. All w o rk in this

building is complete.

6

 

mUSD

Manteca Unified School District

WESTON RANCH HIGH SCHOOL –PHASE II

The second phase of Weston Ranch High School includ es a speech-arts building (theatre), two (2)

m u sic/dram a classroom s, sm all gy m n asium , and eighteen (18) classroom s. This facility should house

approxim a tely 600 students.

• General Contractor: F & H Construction

• Lease-Back Agreem ent Date: June 9, 2003

• Original Contract Sum : $7,939,179.02

• Start Date: June 9, 2003

• Net Contract Change by Change Orders: 0

• Current Contract Sum Including A ll Approved Change Orders: $7,939,179.02

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $7,939,179.02

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: N/A

• Total Amount Paid to Contractor to Date: $2,223,570.84

• Total Amount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: $5,715,608.18

• Percentage of Project Com p lete: 28%

• Anticipated Com p letion Date: August 2003

• Building Square Footage 45,948

• Covered Walkway Square Footage 21,448

• Total Square Footage 67,396

• Construction Cost Per Square Foot $143.09

• Funding Sources CFD 1 (Mello Roos)

CFD 2 (Mello Roos)

Fund 35 (State Funds)

City Contribution

• Estim ated Project Budget SITE $250,000.00

PLANS $550,000.00

CONSTRUCTION $7,939,179.02

INSPECTIONS $100,000.00

TESTS $100,000.00

FURN & EQUIPMENT $700,000.00

C O N T I N G E N C I E S $963,371.97

TOTAL $10,602,550.99

7

 

mUSD

Manteca Unified School District

• MISCELLANEOUS INFO

Lease-Back Agreem ent also includes WRHS P ool, WRHS Stadium , and SHS Stadium . The

sm all gy m n asium is a joint-use project with the City of Stockton.

Project rem a ins on schedule for a late Septem be r 2003 com p letion date for two classroom wings

adjacent to the quad. The second gym nasium , Speech Arts, Band Room , and Swim m i ng Pool are

scheduled to be com p leted by Septem ber 2004.

Phase II Classroom Building 8.

Exterior footings placed. Slab on

grade schedule to be placed the w eek

of 5/5. View of the Primary

Gymnasium in background.

Phase II Classroom w i ng 10. Slab

on grade complete. Anchor bolts,

rough electric and plumbing

stubbed in. Walls to be raised the

w eek of 5/5/03.

8

 

mUSD

Manteca Unified School District

Phase II, F& H pre-fabing w a lls to ensure the scheduled completion date is met. Main

Gymnasium is in the background.

9

 

mUSD

Manteca Unified School District

WALTER E. WOODWARD ELEMENTARY SCHOOL –PHASE I

 

This school is located on a fourteen (14) acre site. Phase I of this project includes an

adm i nistration building with six (6) offices, two (2) classroom s, restroom facilities, teachers’

workroom , sick room , clerical work area. The m u lti-use building is also included in this phase.

The kitchen is a production kitchen and the students’ eating area m a y be converted to use for

indoor sports or for perform ing arts.

• General Contractor: Span Construction

• Contract Date: May 15, 2002

• Original Contract Sum : $5,170,000.00

• Start Date: May 28, 2002

• Net Contract Change by Change Orders: $52,421.00

• Current Contract Sum Including All Approved Change Orders: $5,222,421.00

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $5,222,421.00

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: 1%

• Total Am ount Paid to Contractor to Date: $4,161,399.12

• Total Am ount W ithheld as Retention to Date: $462,377.68

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: N/A

• Percentage of Project Com p lete: 88.5%

• Anticipated Com p letion Date: August 2003

• Square Footage 23,276.09

• Cost Per Square Foot $224.37

• Funding Source Fund 25 (Developer Fees)

Fund 35 (State Funds)

CFD 2 (Mello Roos)

CFD 3 ( Mello Roos)

• Estim ated Project Budget SITE $1,900,000.00

PLANS $700,000.00

CONSTRUCTION $12,574,455.78

INSPECTIONS $150,000.00

TESTS $200,000.00

FURN & EQUIPMENT $200,000.00

C O N T I N G E N C I E S $150,000.00

TOTAL $15,874,455.78

*FIGURES ARE FOR PHASE I & PHASE II

10

 

mUSD

Manteca Unified School District

 

Installation of the roof truss

system on the Multipurpose

Room .

Exterior view of the

sheeting process on the

Multipurpose room at

W oodward School.

11

 

mUSD

Manteca Unified School District

Exterior view of the

Administrative offices at

Woodward School. Interior

sheetrock is in progress.

Exterior view of the

Multipurpose Building af ter the

roof was com p leted.

12

 

mUSD

Manteca Unified School District

View from the parking areas looking at the Adm i nistrative and Multipurpose Buildings at W a lter

W oodward School.

13

 

mUSD

Manteca Unified School District

WALTER E. WOODWARD ELEMENTARY SCHOOL –PHASE II

This phase of the project includes restroom s, storage f acilities, library, com puter lab, and f o rty

(40) m a nufactured (Saram ark) buildings. This phase of the project was based on a cooperative

purchase agreem ent (piggyback) that is in place with Mount Pleasant Elem entary School

District.

• General Contractor: Bruns Belmont Construction / Saramark

• Contract Date: Approximately July 1, 2003

• Original Contract Sum : $6,799,295.00

• Start Date: Approxim a tely July 1, 2003

• Net Contract Change by Change Orders: N/A

• Current Contract Sum Including All Approved Change Orders: $6,799,295.00

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $6,799,295.00

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: 0%

• Total Am ount Paid to Contractor to Date: $0.00

• Total Am ount Held in Escrow Account as Retention to Date: $0.00

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: $6,799,295.00

• Percentage of Project Com p lete: 0%

• Anticipated Date of Com p letion: June 2004

• Square Footage Approxim a tely 37,518

• Cost Per Square Foot $181.23

• Funding Source Fund 25 (Developer Fees)

Fund 35 (State Funds)

CFD 2 (Mello Roos)

CFD 3 (Mello Roos)

• Estim ated Project Budget SITE $1,900,000.00

PLANS $700,000.00

CONSTRUCTION $12,574,455.78

INSPECTIONS $150,000.00

TESTS $200,000.00

FURN & EQUIPMENT $200,000.00

C O N T I N G E N C I E S $150,000.00

14

 

mUSD

Manteca Unified School District

TOTAL $15,874,455.78

*FIGURES ARE FOR PHASE I & PHASE II

WALTER E. WOODWARD ELEMENTARY SCHOOL –PHASE III

This project includes landscaping, concrete flatwork, low voltage com m unication

system (speakers/bells/security system /phones/ clocks/com puter wiring), kindergarten and

prim ary grades’ playground equipm ent, fenci ng and gates along Sundance Street, exterior

 

lighting, tetherball, basketball, four-square courts, site electrical distribution and final

 

connections for all utilities at each building with closure panels and concrete at each end of

building.

• General Contractor:

• Contract Date:

• Original Contract Sum : $1,500,000 ESTIMATE

• Start Date: January 2004

• Net Contract Change by Change Orders:

• Current Contract Sum Including All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s:

• Total Am ount Paid to Contractor to Date:

• Total Am ount W ithheld as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete:

• Anticipated Com p letion Date: June 2004

• Square Footage

• Cost Per Square Foot

• Funding Source Fund 25 (Developer Fees)

Fund 35 (State Funds)

CFD 2 (Mello Roos)

CFD 3 (Mello Roos)

• Estim ated Project Budget PLANS $25,000.00

CONSTRUCTION $1,500,000.00

INSPECTIONS $15,000.00

T E S T S $500.00

15

 

mUSD

Manteca Unified School District

TOTAL $1,540,500.00

VERITAS ELEMENTARY SCHOOL

This project consists of an adm i nistration building, three (3) kindergarten classroom s, teachers’

workroom , com puter lab, thirty-eight (38) classroom s –which include science labs, library,

storage building, and a m u lti-use building which houses a kitchen, storage, indoor basketball

courts, and restroom s.

• General Contractor: F & H Construction

• Contract Date: May 14, 2003

• Original Contract Sum : $10,969,000.00

• Start Date: May 28, 2003

• Net Contract Change by Change Orders: N/A

• Current Contract Sum Including All Approved Change Orders: $10,969,000.00

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $10,969,000.00

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: N/A

• Total Am ount Paid to Contractor to Date: $382,023.58

• Total Am ount Held in Escrow Account as Retention to Date: $0

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: $10,586,976.42

• Percentage of Project Com p lete: 3.5%

• Anticipated Date of Com p letion: November 2004

• Building Square Footage 65,660

• Covered W a lkway Square Footage 24,154

• Total Square Footage 89,814

• Cost Per Square Foot $122.13

• Funding Source Fund 22 (Redevelopm ent)

Fund 25 (Developer Fees)

Fund 35 (State Funds)

• Estim ated Project Budget SITE $1,500,000.00

PLANS $600,000.00

CONSTRUCTION $11,000,000.00

INSPECTIONS $100,000.00

16

 

mUSD

Manteca Unified School District

TESTS $60,000.00

FURN & EQUIPMENT $400,000.00

CONTINGENCIES $200,000.00

TOTAL $13,860,000.00

Future site for Veritas School.

North side looking across the

school site.

Pads being com p acted and cut for

the Adm i nistration, Kindergarten,

and Multipurpose Buidlings.

 

17

 

mUSD

Manteca Unified School District

AUGUST KNODT, JR. (DONALD T. EGUSA) GYMNASIUM

This project includes restroom s, snack bar, storage, two (2) team room s and a 76’ x 100’

gym nasium for indoor basketball and volleyball gam e s.

• General Contractor: The McDonald Glenn Company

• Contract Date: February 28, 2003

• Original Contract Sum : $1,816,481.00

• Start Date: March 27, 2003

• Net Contract Change by Change Orders: N/A

• Current Contract Sum Including All Approved Change Orders: $1,816,481.00

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $1,816,481.00

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: 0%

• Total Am ount Paid to Contractor to Date: $612,879.80

• Total Am ount Held in Escrow Account as Retention to Date: $68,097.75

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: $1,135,503.45

• Percentage of Project Com p lete: 37.5%

• Anticipated Date of Com p letion: March 2004

• Square Footage 9,858

• Cost Per Square Foot $184.27

• Funding Source Fund 25 (Developer Fees)

Fund 30 (State Funds)

Interest Earned

City of Stockton Contribution

• Estim ated Project Budget SITE $3,000.00

PLANS $150,000.00

CONSTRUCTION $1,816,481.00

INSPECTIONS $45,000.00

TESTS $16,448.00

TOTAL $2,030,929.00

 

18

 

mUSD

Manteca Unified School District

• MISCELLANEOUS INFO

The new multipurpose building under constructi on at August Knodt looking south tow a rd

the cafeteria. Exterior stem w a ll forms in pl ace for concrete placement of slab on grade.

19

View looking West at

front entrance to the

new building.

 

mUSD

Manteca Unified School District

SEQUOIA MULTI-PURPOSE BUILDING

This project includes a gym nasium large enough for a full size basketball court. The gym nasium

has retractable bleachers and has an approxim a te capacity of 700 persons. The design also

features a kitchen, food storage area, kitchen office , locker room and staff restroom . In addition,

storage space for chairs and tables, m e n and wom e n’s restroom s, janitor’s room and two lobbies

are provided.

• General Contractor: Opinski Construction

• Contract Date: January 23, 2003

• Original Contract Sum : $2,691,788.00

• Start Date: February 10, 2003

• Net Contract Change by Change Orders: N/A

• Current Contract Sum Including All Approved Change Orders: $2,691,788.00

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $2,691,788.00

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: 0%

• Total Am ount Paid to Contractor to Date: $758,445.68

• Total Am ount Held in Escrow Account as Retention to Date: $84,271.75

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: $1,849,070.57

• Percentage of Project Com p lete: 31.3%

• Anticipated Date of Com p letion: February 2004

• Square Footage 10,964

• Cost Per Square Foot $245.52

• Funding Source Fund 25 (Developer Fees)

Fund 30 (State Funds)

Fund 14 (Deferred Maintenance)

Interest Earned

• Estim ated Project Budget SITE $3,000.00

PLANS $150,000.00

CONSTRUCTION $2,691,700.00

INSPECTIONS $20,000.00

20

 

mUSD

Manteca Unified School District

TESTS $45,000.00

FURN & EQUIPMENT $96,960.11

TOTAL $3,006,660.11

North view of the new

m u ltipurpose building.

Caf e teria slab is in

place and with gym

por5ion scheduled to

be poured.

21

View from East to W e st

of the new parking lot

area at Sequoia.

 

mUSD

Manteca Unified School District

SIERRA HIGH SCHOOL STADIUM

Hom e Bleachers have16 rows with 2,840 seats and 30 wheelchair seats. At the top of the

 

bleachers is a 36’ x 8’ press box. The Visitors’ Bleachers have 16 rows with 1,015 seats and 12

wheelchair seats. Restroom s have separate entrances and f acilities f o r the visitors’ and hom e

 

sides. They are located behind the snackbar and are constructed of 7’ concrete block with wood

 

stud walls above. The snackbar is is 24’ x 13’4” with a 12’x13’ storage room next to it. Both

buildings are located at the North end of the stadium . There will be an em ergency generator in

case of a power outage.

• General Contractor: F & H CONSTRUCTION

• Contract Date: June 9, 2003

• Original Contract Sum : $1,150,291.00

• Start Date: June 9, 2003

• Net Contract Change by Change Orders: N/A

• Current Contract Sum Including All Approved Change Orders: $1,150,291.00

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $1,150,291.00

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: N/A

• Total Am ount Paid to Contractor to Date: $0

• Total Am ount Held in Escrow Account as Retention to Date: $0

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: $1,150,291.00

• Percentage of Project Com p lete: 0%

• Anticipated Date of Com p letion: June 2004

Contractor guarantees com p letion by: October 2004

• Press Box Square Footage 288

• Snack Bar/Restrm S q u a r e F o o t a g e 1 , 4 3 5

• Total Square Footage 1,723

• Cost for snack bar/restroom s $177,900.00

. Cost per square footage $123.97

• Funding Source Lease Lease-Back Agreem ent

Fundraising

• Estim ated Project Budget PLANS $250,000.00

CONSTRUCTION $1,150,291.00

22

 

mUSD

Manteca Unified School District

INSPECTIONS $10,000.00

TESTS $5,000.00

FURN & EQUIPMENT $150,000.00

TOTAL $1,565,291.00

View of the

walkways being cut

for access to the

bleacher areas at the

new stadium at

Sierra High School.

23

View of the pads for the

new restroom s and snack

bar at the new stadium .

 

mUSD

Manteca Unified School District

WESTON RANCH HIGH SCHOOL JOINT-USE GYM

The gym is included in Phase II of the W e ston Ranch High School. The City of Stockton has

entered into a Joint-Use Agreem ent with the MUSD f o r this project. The Joint-Use portion

includes the actual gym , restroom s, hall, lobby, and team room .

• General Contractor: F & H CONSTRUCTION

• Contract Date: June 9, 2003

• Original Contract Sum : $1,575,215.98

• Start Date: June 9, 2003

• Net Contract Change by Change Orders: N/A

• Current Contract Sum Including All Approved Change Orders: $1,575,215.98

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $1,575,215.98

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: N/A

• Total Am ount Paid to Contractor to Date: $0

• Total Am ount Held in Escrow Account as Retention to Date: $0

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: $1,575,215.98

• Percentage of Project Com p lete: 0%

• Anticipated Date of Com p letion: August 2004

• Total Square Footage 10,397

• Cost Per Square Foot $151.51

• Funding Source Fund 25 (Developer Fees)

CFD 1 (Mello Roos)

CFD 2 (Mello Roos)

City of Stockton Contribution

• Estim ated Project Budget PLANS $250,000.00

CONSTRUCTION $1,575,215.98

INSPECTIONS $40,000.00

TESTS $50,000.00

FURN & EQUIPMENT $150,000.00

24

 

mUSD

Manteca Unified School District

C O N T I N G E N C I E S $533,717.02

TOTAL $2,598,933.00

• MISCELLANEOUS INFO

Lease-Back Agreem ent also includes W R HS Phase II, W R HS Stadium , and SHS

Stadium

WESTON RANCH HIGH SCHOOL SWIMMING POOL

8 lanes wide, 25 yards long, 6’6” deep. There is a teaching area 20’ wide with a beginning depth

of 2’ 6” sloping to 4’ 6”. The pool has 18 underw ater lights and 8 overhead lights. The surface

 

area of the pool is 6,564 square feet. The pool is surrounded by a concrete deck between 25’ and

40’ wide (depending on side of pool). On Nort h & South sides of pool there is a turf area

between 35’ and 40’ wide. There is a concrete block pool equipm ent building. All is enclosed

in a 8’ high chain link fence.

 

• General Contractor: F & H CONSTRUCTION

• Contract Date: June 9, 2003

• Original Contract Sum : $862,000.00

• Start Date: June 9, 2003

• Net Contract Change by Change Orders: N/A

• Current Contract Sum Including All Approved Change Orders: $862,000.00

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $862,000.00

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: N/A

• Total Am ount Paid to Contractor to Date: $0

• Total Am ount Held in Escrow Account as Retention to Date: $0

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: $862,000.00

• Percentage of Project Com p lete: 0%

• Anticipated Date of Com p letion: August 2004

• Funding Source Fund 25 (Developer Fees)

CFD 1 (Mello Roos)

CFD 2 (Mello Roos)

City of Stockton Contribution

• Estim ated Project Budget PLANS $75,000.00

CONSTRUCTION $862,000.00

INSPECTIONS $10,000.00

TESTS $3,000.00

25

 

mUSD

Manteca Unified School District

FURN & EQUIPMENT $50,000.00

TOTAL $1,000,000.00

• MISCELLANEOUS INFO

Lease-Back Agreem ent also includes W R HS Phase II, W R HS Stadium , and SHS

Stadium

26

 

mUSD

Manteca Unified School District

WESTON RANCH HIGH SCHOOL STADIUM

Hom e Bleachers have16 rows with 2,840 seats and 30 wheelchair seats. At the top of the

 

bleachers is a 36’ x 8’ press box. The Visitors’ Bleachers have 16 rows with 1,015 seats and 12

wheelchair seats. Restroom s have separate entrances and f acilities f o r the visitors’ and hom e

 

sides. They are located behind the snackbar and are constructed of 7’ concrete block with wood

 

stud walls above. The snackbar is is 24’ x 13’4” with a 12’x13’ storage room next to it. Both

buildings are located at the North end of the stadium . Also, 4 pole m ounted stadium lights shall

be provided. There will be an em ergency generator in case of a power outage.

• General Contractor: F & H CONSTRUCTION

• Contract Date: June 9, 2003

• Original Contract Sum : $1,390,933.00

• Start Date: June 9, 2003

• Net Contract Change by Change Orders: N/A

• Current Contract Sum Including All Approved Change Orders: $1,390,933.00

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $1,30,933.00

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: N/A

• Total Am ount Paid to Contractor to Date: $0

• Total Am ount Held in Escrow Account as Retention to Date: $0

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: $1,390,933.00

• Percentage of Project Com p lete: 0%

• Anticipated Date of Com p letion: June 2004

Contractor guarantees com p letion by: October 2004

• Press Box Square Footage 288

• Snack Bar Square Footage 1,435

• Total Square Footage 1,723

• Cost Per Square Foot $123.97

• Funding Source Lease Lease-Back Agreem ent

CFD 1 (Mello Roos)

• Estim ated Project Budget PLANS $250,000.00

CONSTRUCTION $1,390,933.00

INSPECTIONS $10,000.00

TESTS $5,000.00

FURN & EQUIPMENT $150,000.00

27

 

mUSD

Manteca Unified School District

TOTAL $1,805,933.00

• MISCELLANEOUS INFO

Lease-Back Agreem ent also includes W R HS Phase II, W R HS Pool, and SHS Stadium

28

 

mUSD

Manteca Unified School District

4 RELOCATABLES AT NILE GARDEN

This project is com p rised of four (4) ModTech m a nufactured buildings from the Em ergency

State Relocatables Program .

• General Contractor: Rodgers Construction

• Contract Date: May 16, 2003

• Original Contract Sum : $135,959.00

• Start Date: June 3, 2003

• Net Contract Change by Change Orders: N/A

• Current Contract Sum Including All Approved Change Orders: $135,959.00

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $135,959.00

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: N/A

• Total Am ount Paid to Contractor to Date: $62,693.10

• Total Am ount Held in Escrow Account as Retention to Date: $6,965.90

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: $66,300.00

• Percentage of Project Com p lete: 52%

• Anticipated Date of Com p letion: August 2003

• Square Footage 3,840

• Cost Per Square Foot $35.41

• Funding Source Fund 25 (Developer Fees)

Fund 30 (State Funds)

• Estim ated Project Budget PLANS $50,000.00

CONSTRUCTION $135,959.00

INSPECTIONS $20,000.00

TESTS $5,000.00

FURN & EQUIPMENT $.00

TOTAL $210,959.00

• MISCELLANEOUS INFO

Standard eligibility to be approved for these buildings is based on the num ber of teaching

stations approved but not yet constructed pursuant to the school facility program .

Eligibility m a y also be approved by the one (1) year projections f o r average daily

attendance (ADA) as determ ined on the enrollm ent certification projection.

29

 

mUSD

Manteca Unified School District

District m a kes a lease paym ent of $4,000 /bldg per year and receives $9,450/clsrm for

reim bursem e nts for expenditures during the planning, construction, as well as furniture

and equipm ent phases.

30

 

mUSD

Manteca Unified School District

6 RELOCATABLES AT GREAT VALLEY SCHOOL

This project is com p rised of six (6) ModTech m a nufactured buildings from the Em ergency State

Relocatables Program .

• General Contractor: Barham Construction

• Contract Date: May 27, 2003

• Original Contract Sum : $238,938.00

• Start Date: June 3, 2003

• Net Contract Change by Change Orders: N/A

• Current Contract Sum Including All Approved Change Orders: $226,817.00

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $238,938.00

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: 0%

• Total Am ount Paid to Contractor to Date: $0.00

• Total Am ount Held in Escrow Account as Retention to Date: $0.00

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: $238,938.00

• Percentage of Project Com p lete: 0%

• Anticipated Date of Com p letion: August 2003

• Square Footage 5,760

• Cost Per Square Foot $41.49

• Funding Source Fund 25 (Developer Fees)

Fund 30 (State Funds)

• Estim ated Project Budget PLANS $30,000.00

CONSTRUCTION $238,938.00

INSPECTIONS $15,000.00

TESTS $2,500.00

FURN & EQUIPMENT $12,000.00

TOTAL $298,438.00

• MISCELLANEOUS INFO

31

Standard eligibility to be approved f o r these buildings is based on the num ber of teaching

stations approved but not yet constructed pursuant to the school facility program .

Eligibility m a y also be approved by the one (1) year projections f o r average daily

attendance (ADA) as determ ined on the enro llm ent certification projection. District

 

mUSD

Manteca Unified School District

m a kes a lease paym ent of $4,000 /bldg pe r year and receives $9,450/clsrm for

reim bursem e nts for expenditures during the pl anning, construction, as well as furniture

and equipm ent phases.

32

 

mUSD

Manteca Unified School District

9 RELOCATABLES AT NEW HAVEN

These nine (9) State Em ergency Portables were originally at East Union.

• General Contractor: PENDING

• Contract Date:

• Original Contract Sum : $360,000.00 ESTIMATE

• Start Date: July 9, 2003

• Net Contract Change by Change Orders: N/A

• Current Contract Sum Including All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

N/A •

Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: N/A

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete: 0%

• Anticipated Date of Com p letion: August 2003

• Square Footage 8,640

• Cost Per Square Foot $41.67 ESTIMATED

• Funding Source Fund 25 (Developer Fees)

• Estim ated Project Budget PLANS $60,000.00

CONSTRUCTION $360.000.00

INSPECTIONS $5,000.00

TESTS $1,000.00

TOTAL $426,000.00

• MISCELLANEOUS INFO

33

 

mUSD

Manteca Unified School District

10 RELOCATABLES AT VARIOUS SITES

6-Sierra High School / 3-Lincoln Elementary / 1-Sequoia Annex

This project is com p rised of ten (10) ModTech m a nufactured buildings from the Em ergency

State Relocatables Program .

• General Contractor: AM Stephens Construction

• Contract Date: May 16, 2003

• Original Contract Sum : $176,300.00

• Start Date: June 3, 2003

• Net Contract Change by Change Orders: N/A

• Current Contract Sum Including All Approved Change Orders: $176,300.00

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $176,300.00

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: 0%

• Total Am ount Paid to Contractor to Date: $84,069.00

• Total Am ount Held in Escrow Account as Retention to Date: $9,341.00

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: $82,890.00

• Percentage of Project Com p lete 53%

• Anticipated Date of Com p letion: August 2003

• Square Footage 9,600

• Cost Per Square Foot $18.37

• Funding Source Fund 25 (Developer Fees)

Fund 30 (State Funds)

• Estim ated Project Budget PLANS $30,000.00

CONSTRUCTION $176,300.00

INSPECTIONS $15,000.00

TESTS $2,500.00

FURN & EQUIPMENT $20,000.00

TOTAL $243,800.00

• MISCELLANEOUS INFO

Standard eligibility to be approved f o r these buildings is based on the num ber of teaching

stations approved but not yet constructed pursuant to the school facility program .

Eligibility m a y also be approved by the one (1) year projections f o r average daily

34

 

mUSD

Manteca Unified School District

attendance (ADA) as determ ined on the enro llm ent certification projection. District

m a kes a lease paym ent of $4,000 /bldg per year and receives $9,450/clsrm for

reim bursem e nts for expenditures during the pl anning, construction, as well as furniture

and equipm ent phases.

Sierra Highs School State

Portables being set to grade.

Sierra High School State

Portables being set for

electrical and data conduits.

35

 

mUSD

Manteca Unified School District

Sequoia Annex new State

Portable for Reading

Recovery.

Lincoln State Portables being

set to grade.

 

36

 

mUSD

Manteca Unified School District

10 RELOCATABLES AT VARIOUS SITES

3-Lathrop / 2-August Knodt / 2-Golden West / 2-Stella Brockman / 1-French Camp

This project is com p rised of ten (10) ModTech m a nufactured buildings from the Em ergency

State Relocatables Program .

• General Contractor: McDonald Glenn

• Contract Date: May 16, 2003

• Original Contract Sum : $222,225.00

• Start Date: June 3, 2003

• Net Contract Change by Change Orders: N/A

• Current Contract Sum Including All Approved Change Orders: $222,225.00

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders: $222,225.00

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: N/A

• Total Am ount Paid to Contractor to Date: $139,495.32

• Total Am ount Held in Escrow Account as Retention to Date: $15,499.48

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent: $67,230.20

• Percentage of Project Com p lete 31%

• Anticipated Date of Com p letion: August 2003

• Square Footage 9,600

• Cost Per Square Foot $23.15

• Funding Source Fund 25 (Developer Fees)

Fund 30 (State Funds)

• Estim ated Project Budget PLANS $30,000.00

CONSTRUCTION $222,225.00

INSPECTIONS $15,000.00

TESTS $2,500.00

FURN & EQUIPMENT $20,000.00

TOTAL $289,725.00

• MISCELLANEOUS INFO

37

Standard eligibility to be approved f o r these buildings is based on the num ber of teaching

stations approved but not yet constructed pursuant to the school facility program .

Eligibility m a y also be approved by the one (1) year projections f o r average daily

 

mUSD

Manteca Unified School District

attendance (ADA) as determ ined on the enro llm ent certification projection. District

m a kes a lease paym ent of $4,000 /bldg per year and receives $9,450/clsrm for

reim bursem e nts for expenditures during the pl anning, construction, as well as furniture

and equipm ent phases.

Two State Portables beings

setup at Stella Brockm an.

38

 

mUSD

Manteca Unified School District

5

th

HIGH SCHOOL (LATHROP) -PROPOSED

The school w ill be located on approximately fifty (50) acres. The high school w ill consist of an

administration building, library, tw enty-eight ( 28) classrooms, six (6) science labs, seven (7)

business labs, three(3) shops, cafeteria, large gym , small gym, boys’ and girls’ locker rooms,

speech arts building (theatre), and tw o (2) music/ drama classrooms. The high school should

house approximately 1,600 students.

• General Contractor:

• Contract Date:

• Original Contract Sum : $31,08,140.00 ESTIMATED

• Anticipated Start Date: July 2006

• Net Contract Change by Change Orders:

• Current Contract Sum Includi ng All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Items:

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete:

• Anticipated Date of Com p letion: July 2008

• Building Square Footage 153,376

• Covered Walkway Square Footage 58,915

• Total Square Footage 212,291

• Cost Per Square Foot

• Funding Source Fund 25 (Developer Fees)

Fund 35 (State Funds)

CFD 2 (Mello Roos)

• Estim ated Project Budget SITE $7,500,000.00

PLANS $1,500,000.00

CONSTRUCTION $35,000,000.00

INSPECTIONS $350,000.00

TESTS $200,000.00

FURN & EQUIPMENT $1,500,000.00

TOTAL $46,050,000.00

• MISCELLANEOUS INFO

39

 

mUSD

Manteca Unified School District

This high school is proposed due to the fact that there are plans for

approxim a tely 8,400 new hom es in the next 5-10 years West of I-5

(Lathrop). The CDE has done a prelim inary review of the proposed

school site.

40

 

mUSD

Manteca Unified School District

20 RELOCATABLES AT VARIOUS SITES

 

This project will be presented for State Allocation Board approval on July 23, 2003.

• General Contractor: PENDING

• Contract Date:

• Original Contract Sum : $400,000.00 ESTIMATE

• Start Date: Approxim a tely September 2003

• Net Contract Change by Change Orders: N/A

• Current Contract Sum Including All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent: N/A

• Unresolved Change Orders in Dispute with Contractor: N/A

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s: N/A

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete: 0%

• Anticipated Date of Com p letion: Approxim a tely December 2003

• Square Footage 19,200

• Cost Per Square Foot $20.84 ESTIMATE

• Funding Source Fund 25 (Developer Fees)

Fund 30 (State Funds)

• Estim ated Project Budget PLANS $60,000.00

CONSTRUCTION $400,000.00

INSPECTIONS $6,000.00

TESTS $1,000.00

FURN & EQUIPMENT $40,000.00

 

TOTAL $507,000.00

• MISCELLANEOUS I N F O

The District m a kes lease paym ents of $4,000/year for each relocatable. The State reim burses

the District $9,450/clsrm for the following expenditures: DSA plans ? $450; Architect’s fees

? $2,000; Electrical hook-up fees ? $3,500; Fire alarm hook-up fees ? $1,000; Inspection costs

? $500; and Furniture & Equipm ent ? $2,000.

41

 

mUSD

Manteca Unified School District

CALLA HIGH SCHOOL (CITY) WATER LINE ADDITION

• General Contractor:

• Contract Date:

• Original Contract Sum : $135,828.00

• Anticipated Start Date:

• Net Contract Change by Change Orders:

• Current Contract Sum Including All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s:

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete:

• Anticipated Date of Com p letion:

• Funding Source Fund 14 (Deferred Maintenance)

Fund 25 (Developer Fees)

• Estim ated Project Budget

PLANS $1,500.00

CONSTRUCTION $135,828.00

INSPECTIONS -City to Inspect

TOTAL $137,328.00 +/-

• MISCELLANEOUS INFO

On 6/28/02 the City of Manteca appr oved the annexation of Calla High

School to the City of Manteca. The annexation was required due to

expanding the Calla High School cam pus with additional portables. The

 

local fire departm e nt requested th at we pursue City water hook-ups for

adequate fire protection at the Calla site.

42

 

mUSD

Manteca Unified School District

DISTRICT OFFICE BUS WASH

• General Contractor:

• Contract Date:

• Original Contract Sum : $54,000 ESTIMATE

• Anticipated Start Date: October 2003

• Net Contract Change by Change Orders:

• Current Contract Sum Including All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s:

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete:

• Anticipated Date of Com p letion: January 2004

• Total Square Footage

• Cost Per Square Foot

• Funding Source Fund 25 (Developer Fees)

• Estim ated Project Budget PLANS $30,000

CONSTRUCTION $54,000

INSPECTIONS $5,000

TESTS $2,000

TOTAL $91,000

• MISCELLANEOUS INFO

ATI Architects recently designed a bus wash for the San Ram on School District. The

MUSD is working with the architect on design and plans.

43

 

mUSD

Manteca Unified School District

EAST UNION HIGH SCHOOL BAND ROOM CONVERSION TO

CLASSROOMS

• General Contractor:

• Contract Date:

• Original Contract Sum : $679,000.00 ESTIMATE

• Anticipated Start Date: January 2004

• Net Contract Change by Change Orders:

• Current Contract Sum Including All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s:

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete:

• Anticipated Date of Com p letion: April 2004

• Building Square Footage 3,840

• Cost Per Square Foot

• Funding Source Fund 25 (Developer Fees)

• Estim ated Project Budget SITE $3,000.00

PLANS $80,000.00

CONSTRUCTION $679,000.00

INSPECTIONS $36,000.00

TESTS $2,000.00

TOTAL $800,000.00

• MISCELLANEOUS INFO

Due to the com p letion of the perm anent band room , the existing portable band

room is scheduled to be converted into three (3) classroom s.

44

 

mUSD

Manteca Unified School District

EAST UNION HIGH SCHOOL GYMS / SHOPS MODERNIZATION /

EXPANSION

• General Contractor:

• Contract Date:

• Original Contract Sum : $1,500,000.00 ESTIMATED

• Anticipated Start Date: May 2004

• Net Contract Change by Change Orders:

• Current Contract Sum Including All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s:

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete:

• Anticipated Date of Com p letion: November 2004

• Building Square Footage 42,635

• Covered W a lkway Square Footage

• Total Square Footage

• Cost Per Square Foot

• Funding Source Fund 35 (State Funds)

 

• Estim ated Project Budget

PLANS $200,000.00

CONSTRUCTION $1,500,000.00

INSPECTIONS $24,000.00

TESTS $3,000.00

FURN & EQUIPMENT $150,000.00

TOTAL $1,877,000.00

• MISCELLANEOUS INFO

Plans and specifications have been approved by DSA and are awaiting

funding apportionm ent from the State.

45

 

mUSD

Manteca Unified School District

FRENCH CAMP ELEMENTARY SCHOOL LIBRARY / CLASSROOM

MODERNIZATION

This project includes six (6) classroom s and the library. The room s will be m odernized with

new HVAC units, new carpet, new electrical, and new dry erase boards.

• General Contractor:

• Contract Date:

• Original Contract Sum : $736,954 ESTIMATE

• Anticipated Start Date: Sum m e r 2004

• Net Contract Change by Change Orders:

• Current Contract Sum Including All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s:

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete:

• Anticipated Date of Com p letion: Fall 2004

• Building Square Footage

• Covered W a lkway Square Footage

• Total Square Footage 7,519

• Cost Per Square Foot $98.02 ESTIMATE

• Funding Source Fund 25 (Developer Fees)

Fund 35 (State Funds)

• Estim ated Project Budget PLANS $50,000

CONSTRUCTION $736,954

INSPECTIONS $20,000

TESTS $2,500

FURN & EQUIPMENT $60,000

CONTINGENCIES $100,000

TOTAL $969,454

46

 

mUSD

Manteca Unified School District

GREAT VALLEY ANNEX

This project includes twelve (12) standard cla ssroom s, restroom s, storage, eight (8) portable

classroom s, adm i nistration building, com puter lab, library, and a portable m u lti-use building

with a Food Service serving kitchen.

• General Contractor:

• Contract Date:

• Original Contract Sum : $6,700,000.00 ESTIMATE

• Anticipated Start Date: Novem b er 2003

PROJECT CURRENTLY IN PLANNING STAGE

• Net Contract Change by Change Orders:

• Current Contract Sum Includi ng All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pe nding Change Orders Item s:

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Complete:

• Anticipated Date of Completion:

• Building Square Footage 20,435

• Portables 11,808

• Covered Walkway Square Footage 4,652

• Total Square Footage 36,895

• Cost Per Square Foot $181.60 ESTIMATE

• Funding Source Fund 25 (Developer Fees)

 

Fund 35 (State Funding)

CFD 1 (Mello Roos)

Cost Savings from Great Valley

Elem entary

• Estim ated Project Budget SITE $1,400,000

PLANS $400,000

CONSTRUCTION $6,700,000

INSPECTIONS $65,000

TESTS $60,000

FURN & EQUIPMENT $200,000

CONTINGENCIES $75,000

47

 

mUSD

Manteca Unified School District

TOTAL $8,900,000

• MISCELLANEOUS INFO

The plans are currently being reviewed by the Departm e nt of the State Architect . It is anticipated that the plans

will be approved in Septem ber of 2003. It is estim ated that the State will approve funding in fall of 2003. The

Depart m e nt of Toxi c Subst a nce C ont rol i s revi ewi ng t h e t e st s on t h e soi l of t h e propert y . W e ant i c i p at e

approval by C D E and DTSC i n t h e end of Jul y or Augus t 2003. Negat i v e Decl arat i on current l y bei ng revi ewed

by the State Clearing House.

48

 

mUSD

Manteca Unified School District

49

 

mUSD

Manteca Unified School District

LATHROP COMMUNITY GYMNASIUM

This gy m n asium is large enough for a full size basketba ll court. The gy m n asium has retractable bleachers

and has an approxim a te capacity of 700 persons. The design also features a kitchen, food storage area,

kitchen office, locker room and staff restroom . In addition, storage space for chairs and tables, m e n and

wom e n’s restroom s, janitor’s room and two lobbies are provided.

• General Contractor:

• Contract Date:

• Original Contract Sum : $1,650,500.00 ESTIMATED

• Anticipated Start Date: October 2003

THIS PROJECT IS IN THE PLANNING STAGE

• Net Contract Change by Change Orders:

• Current Contract Sum Includi ng All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pe nding Change Orders Item s:

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete:

• Anticipated Date of Com p letion: October 2004

• Total Square Footage 10,264

• Cost Per Square Foot

• Funding Source Fund 25 (Developer Fees)

Fund 30 (State Funding)

City of Lathrop Contribution

• Estim ated Project Budget SITE $3,000.00

PLANS $250,000.00

CONSTRUCTION $1,650,500.00

INSPECTIONS $45,000.00

TESTS $20,000.00

FURN & EQUIPMENT $60,000.00

TOTAL $2,028,500.00

• MISCELLANEOUS INFO

We anticipate receiving funds from SB 1795 Joint-U se legislation in August 2003. The project m a y

go out to bid in Septem ber 2003 with an estim ated start date of October 2003.

50

 

mUSD

Manteca Unified School District

MANTECA HIGH SCHOOL FIELD HOUSE

This project includes three (3) classroom s, girls’ and boys’ showers and lockers, restroom s,

coaches’ office, storage, training and team room s.

• General Contractor:

• Contract Date:

• Original Contract Sum : $1,895,000.00 ESTIMATE

• Anticipated Start Date: October 2003

THIS PROJECT IS IN THE PLANNING STAGE

• Net Contract Change by Change Orders:

• Current Contract Sum / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s:

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete:

• Anticipated Date of Com p letion:

• Building Square Footage 8,194

• Cost Per Square Foot

• Funding Source Fundraising

Fund 22 (Re-Developm ent)

Fund 25 (Developer Fees)

Fund 35 (State Funding)

• Estim ated Project Budget SITE $2,000.00

PLANS $100,00.00

CONSTRUCTION $1,895,000.00

INSPECTIONS $56,000.00

TESTS $5,000.00

FURN & EQUIPMENT $30,000.00

TOTAL $2,088,000.00

• MISCELLANEOUS INFO

The plans are being reviewed by DSA. W e anticipate DSA and CDE approval by the

end of July 2003. State allocation of funding is anticipated in Septem ber 2003.

51

 

mUSD

Manteca Unified School District

LATHROP AREA 1 ELEMENTARY SCHOOL

This project consists of an adm i nistration building, three (3) kindergarten classroom s, teachers’

workroom , com puter lab, thirty-eight (38) classroom s –which include science labs, library,

storage building, and a m u lti-use building which houses a kitchen, storage, indoor basketball/

volleyball courts, and restroom s.

• General Contractor:

• Contract Date:

• Original Contract Sum : $11,650,000.00 ESTIMATED

• Anticipated Start Date:

THIS PROJECT IS IN THE PLANNING STAGE

• Net Contract Change by Change Orders:

• Current Contract Sum Including All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s:

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete:

• Anticipated Date of Com p letion:

• Building Square Footage 65,660 ESTIMATED

• Covered W a lkway Square Footage 24,154

• Total Square Footage 89,814

• Cost Per Square Foot $129.71

• Funding Source Fund 25 (Developer Fees)

Fund 35 (State Funds)

• Estim ated Project Budget SITE $2,500,000.00

PLANS $650,000.00

CONSTRUCTION $11,650,000.00

INSPECTIONS $125,000.00

TESTS $75,000.00

FURN & EQUIPMENT $300,000.00

CONTINGENCIES $300,000.00

52

 

mUSD

Manteca Unified School District

TOTAL $15,550,000.00

53

 

mUSD

Manteca Unified School District

54

 

mUSD

Manteca Unified School District

55

 

mUSD

Manteca Unified School District

NILE GARDEN ELEMENTARY PARKING LOT REPAIR / GAS LINE

MOVEMENT

• General Contractor:

• Contract Date:

• Original Contract Sum : $163,092.00 ESTIMATED

• Anticipated Start Date: July 2004

THIS PROJECT IS IN THE PLANNING STAGE

• Net Contract Change by Change Orders:

• Current Contract Sum Including All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s:

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete:

• Anticipated Date of Com p letion:

• Building Square Footage N/A

• Covered W a lkway Square Footage

• Total Square Footage

• Cost Per Square Foot

• Funding Source Fund 14 (Deferred Maintenance)

• Estim ated Project Budget SITE

PLANS

CONSTRUCTION

INSPECTIONS

T E S T S

TOTAL

• MISCELLANEOUS INFO

Plans are available to go out to bid. Anticipated start is sum m e r of 2004 .

56

 

mUSD

Manteca Unified School District

NILE GARDEN ELEMENTARY SCHOOL LIBRARY / CLASSROOM

MODERNIZATION

This project includes ten (10) classroom s and the library. The room s will be m odernized with

new HVAC units, new carpet, widened (handicap accessible) doors, som e updated electrical, and

new dry erase boards.

• General Contractor:

• Contract Date:

• Original Contract Sum : $1,065,254 ESTIMATE

• Anticipated Start Date: Sum m e r 2004

• Net Contract Change by Change Orders:

• Current Contract Sum Including All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s:

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete:

• Anticipated Date of Com p letion: Fall 2004

• Building Square Footage 12,654

• Cost Per Square Foot $84.19 ESTIMATE

• Funding Source Fund 25 (Developer Fees)

• Estim ated Project Budget PLANS $65,000

CONSTRUCTION $1,095,254

INSPECTIONS $20,000

TESTS $5,000

FURN & EQUIPMENT $60,000

CONTINGENCIES $100,000

TOTAL $1,315,254

• MISCELLANEOUS INFO

57

 

mUSD

Manteca Unified School District

LATHROP AREA 2 ELEMENTARY SCHOOL

This project consists of an adm i nistration building, three (3) kindergarten classroom s, teachers’

workroom , com puter lab, thirty-eight (38) classroom s –which include science labs, library,

storage building, and a m u lti-use building which houses a kitchen, storage, indoor basketball/

volleyball courts, and restroom s.

• General Contractor:

• Contract Date:

• Original Contract Sum : $11,650,000.00 ESTIMATED

• Anticipated Start Date:

THIS PROJECT IS IN THE PLANNING STAGE

• Net Contract Change by Change Orders:

• Current Contract Sum Including All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s:

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete:

• Anticipated Date of Com p letion:

• Building Square Footage 65,660 ESTIMATED

• Covered W a lkway Square Footage 24,154

• Total Square Footage 89,814

• Cost Per Square Foot $129.71

• Funding Source Fund 25 (Developer Fees)

Fund 35 (State Funds)

• Estim ated Project Budget SITE $2,500,000.00

PLANS $650,000.00

CONSTRUCTION $11,650,000.00

INSPECTIONS $125,000.00

TESTS $75,000.00

FURN & EQUIPMENT $300,000.00

CONTINGENCIES $250,000.00

58

 

mUSD

Manteca Unified School District

TOTAL $15,550,000.00

59

 

mUSD

Manteca Unified School District

60

 

mUSD

Manteca Unified School District

ROBERTSON PROPERTY

This project consists of an adm i nistration building, three (3) kindergarten classroom s, teachers’

workroom , com puter lab, thirty-eight (38) classroom s –which include science labs, library,

storage building, and a m u lti-use building which houses a kitchen, storage, indoor basketball/

volleyball courts, and restroom s.

• General Contractor:

• Contract Date:

• Original Contract Sum : $11,650,000.00 ESTIMATED

• Anticipated Start Date:

• Net Contract Change by Change Orders:

• Current Contract Sum Including All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pending Change Orders Item s:

• Total Am ount Paid to Contractor to Date:

• Total Am ount Held in Escrow Account as Retention to Date:

• Balance Rem a ining on Total Approved Contract Sum Pending

Approval of Settlem e nt Agreem ent:

• Percentage of Project Com p lete:

• Anticipated Date of Com p letion:

• Building Square Footage 65,660 ESTIMATED

• Covered W a lkway Square Footage 24,154

• Total Square Footage 89,814

• Cost Per Square Foot $129.71

• Funding Source Fund 25 (Developer Fees)

Fund 35 (State Funds)

• Estim ated Project Budget SITE $2,500,000.00

PLANS $650,000.00

CONSTRUCTION $11,650,000.00

INSPECTIONS $125,000.00

TESTS $75,000.00

FURN & EQUIPMENT $300,000.00

CONTINGENCIES $300,000.00

61

 

mUSD

Manteca Unified School District

TOTAL $15,550,000.00

RUSTIC ELEMENTARY SCHOOL

This project includes an administration build ing, teachers’ w o rkroom, multi-use building (w /

indoor basketball/volleyball courts, bleachers, kitchen, cafeteria area, & stage), restrooms,

library, and 43 classrooms. This energy efficien t school has the follow i ng: sky lights; clear

story w i ndow s ; w i ndow s on North side of build ings; A/C units are higher energy efficiency

rated ; less lighting fixtures; lights have automa tic on/off switch es; switches shut-off HVAC if

doors are open; all exterior w i ndow s are dual pane glass. The school itse lf is oriented on the

property so that it maximiz e s the benefits of natural light.

• General Contractor:

• Contract Date:

• Original Contract Sum : $11,000,000.00 ESTIMATE

• Anticipated Start Date: Spring 2004

• Net Contract Change by Change Orders:

• Current Contract Sum Includi ng All Approved Change Orders:

• Pending Change Order Item s Authorized / Negotiated and

Approved by the District Per Settlem e nt Agreem ent:

• Unresolved Change Orders in Dispute with Contractor:

• Final Contract Sum Including All Change Orders:

• Total Percentage of Change Orders to Original Contract Sum

Including All Approved / Pe nding Change Orders Item s:

•